A minor variance is permission to build something that does not fully meet the zoning by-law. In Toronto, the Committee of Adjustment decides each minor variance at a public hearing. Linerra Architects does the zoning review, prepares the drawings and prepares the application for houses, additions, multiplexes, garden suites and small commercial buildings.
The four tests for a minor variance
Section 45(1) of the Planning Act lets the committee approve a variance that meets four tests. The City of Toronto states them like this:
The general intent and purpose of the Official Plan is maintained.
The general intent and purpose of the Zoning By-law is maintained.
The variance is appropriate for the development of the land or the building.
The variance is minor.
A variance must pass all four tests. Common variances for houses are building depth, setbacks, floor area and height.
The steps
Zoning review. Linerra Architects lists each rule that the design does not meet. A zoning review by the City can confirm the list.
Application. The applicant files a complete application with drawings. Since October 1, 2026, the City requires Form A and Form B.
Hearing date and notice. The City sets a hearing date and sends notice to owners within 60 metres at least 10 days before the hearing. The City says applicants typically have 5 to 8 weeks to prepare for their hearing.
Public hearing. The applicant presents the project. Neighbours may speak or write.
Decision. The committee gives a written decision within 10 days.
Appeal period. An appeal of a minor variance decision must be filed within 20 days of the decision. If nobody appeals, the decision is final and binding.
City of Toronto application fees in 2026
These fees took effect on January 1, 2026. Fees for a variance applied for after the work is built are double.
| Application | City fee |
|---|---|
| Minor variance: additions and alterations to an existing dwelling with three units or less | $2,228.98 |
| Minor variance: residential dwellings with three units or less | $5,011.08 |
| Minor variance: all other uses | $6,485.59 |
| Consent (severance): one lot into two | $8,080.65 |
| Consent: each additional lot | $6,561.48 |
Consents (severances)
A consent divides one lot into two or more lots. The Committee of Adjustment also decides consents. For a consent, the City gives 14 days of notice, and the committee usually hears the application within 60 days of a complete application. An appeal must be filed not later than 20 days after notice of the decision is given.
Appeals
Appeals of Committee of Adjustment decisions in Toronto go to the Toronto Local Appeal Body. Under the Planning Act, only the applicant, the Minister, or a specified person or public body may appeal.
Common questions
How long does a minor variance take in Toronto?
The City of Toronto does not state one total time. It says applicants typically have 5 to 8 weeks to prepare for their hearing. Notice goes out at least 10 days before the hearing, the written decision comes within 10 days of the hearing, and the appeal period is 20 days from the decision.
How much does a minor variance cost in Toronto?
In 2026 the City of Toronto fee is $2,228.98 for additions and alterations to an existing dwelling with three units or less, $5,011.08 for residential dwellings with three units or less, and $6,485.59 for all other uses. The fee doubles for work that is already built. The architect's fee for the drawings and the application is separate.
Can I avoid the Committee of Adjustment?
Yes, if the design meets the zoning by-law. Linerra Architects does a zoning review before design starts, so the owner knows early if the project needs a variance or if a small design change removes the need.
What happens if the committee refuses my variance?
The applicant may appeal to the Toronto Local Appeal Body within 20 days of the decision, or change the design and apply again.
Does Linerra Architects prepare Committee of Adjustment applications?
Yes. Linerra Architects prepares the zoning review, the drawings and the application for minor variances and consents in Toronto.
Find out if your project needs a variance
Send Linerra Architects the address of the property and a short note about the project. The first consultation is free. Linerra Architects then reviews the zoning for the lot and sends a written fee proposal.
Start Your Project Call (437) 992-6347
Related pages
Sources
Linerra Architects checked each source on November 25, 2026. Rules change, so confirm the current rule for a specific lot before any design work starts.